NEW PROJECT ANALYSIS Holmes Manufacturing is considering a new machine that costs $250,000 and would reduce pretax manufacturing costs by $90,000 annually. Holmes would use the 3 year MACRS method to depreciate the machine, and management thinks the machine would have a value of $23,000 at the end of its 5 year operating life. The applicable depreciation rates are 33%, 45%, 15%, and 7% as discussed in Appendix 12A. Working capital would increase by $25,000 initially, but it would be recovered at the end of the project’s 5 year life. Holmes’s marginal tax rate is 40%, and a 10%WACCis appropriate for the project.

a. Calculate the project’s NPV, IRR, MIRR, and payback.

b. Assume that management is unsure about the $90,000 cost savings—this figure could deviate by as much as plus or minus 20%. What would the NPV be under each of these situations?

c. Suppose the CFO wants you to do a scenario analysis with different values for the cost savings, the machine’s salvage value, and the working capital (WC) requirement. She asks you to use the following probabilities and values in the scenario analysis:

Scenario

Probability

Cost Savings

Salvage Value

WC

Worst case

0.35

$ 72,000

$18,000

$30,000

Base case

0.35

90,000

23,000

25,000

Best case

0.30

108,000

28,000

20,000

Calculate the project’s expected NPV, its standard deviation, and its coefficient of variation.

Would you recommend that the project be accepted?