Construction Accounting

The Pierson Construction Corporation contracted with the City of Plaquemine to construct a dam on the bayou at a price of $14,000,000. Pierson expects to earn $1,270,000 on the contract. The percentage of completion method is to be used, and the completion stage is to be determined by estimates made by the engineer. The following schedule summarizes the activities of the contract for the years 2007–2009.

 

Cost

Engineer’s Estimated

Estimate of

Billings

Collection

Year

Incurred

Cost to Complete

Completion

on Contract

on Billings

2007

$4,300,000

$8,560,000

33%

$4,000,000

$3,600,000

2008

4,100,000

4,700,000

62

5,000,000

5,100,000

2009

4,550,000

0

100

5,000,000

5,300,000

Instructions:

1. Prepare a schedule showing the revenue, cost, and the gross profit earned each year under the percentage of completion method, using the engineer’s estimate as the measure of completion to be applied to revenues and costs.

2. Prepare all journal entries required to reflect the contract.

3. Prepare journal entries for 2009, assuming the completed contract method is used.

4. How would the journal entries in (2) differ if the actual costs incurred were used to calculate cost for the period instead of the engineer’s estimate?