Percentage of Completion Analysis

Smokey International Inc. recently acquired the Kurtz Builders Company. Kurtz has incomplete accounting records. On one particular project, only the information below is available.

 

2007

2008

2009

Costs incurred during year

$200,000

$250,000

?

Estimated cost to complete

450,000

190,000

$ 0

Recognized revenue

220,000

?

?

Gross profit on contract

?

10,000

(10,000)

Contract price

850,000

 

 

Because the information is incomplete, you are asked the following questions assuming the percentage of completion method is used, an output measure is used to estimate the percentage completed, and revenue is recorded using the actual cost approach.

1. How much gross profit should be reported in 2007?

2. How much revenue should be reported in 2008?

3. How much revenue should be reported in 2009?

4. How much cost was incurred in 2009?

5. What are the total costs on the contract?

6. What would be the gross profit for 2008 if the cost to cost percentage of completion method were used rather than the output measure?