Calculate the direct labour cost variance from the following:

Standard output

=

500 units

Actual output

=

400 units

Standard time per unit

=

5 hrs

Total actual time taken

=

2,200 hrs

Standard rate of wages

=

Rs. 20 per hour

Actual rate of wages

=

Rs. 25 per hour