For the following business, the data relating to the production of one unit is as follows:

Standard materials cost = 4 kg at £3.00 per kg = £12 per unit

Standard labour cost = 2 hours at £5.00 per hour = £10 per unit

If the budgeted output level is 500 units, the standard cost would be as follows:

£

Materials (2,000 kg)

6,000

Labour (1,000 hours)

5,000

Total

11,000

Details of actual production for the forecast period were as follows:

£

Materials

2,050 kg at £2.80 per kg =

5,740

Labour

960 hours at £5.10 per hour =

4,896

Total

10,636

Actual output was 450 units. Although the total cost of £10,636 is lower than the standard cost of £11,000, the actual output was lower than the budgeted output, which means we will need to redraft the budgeted quantities in the light of the actual output. These are as follows:

Materials 450 units × 4 kg = 1,800 kg × £3 = £5,400

Labour 450 units × 2 hours = 900 hours × £5 = £4,500.