Hansen Construction, Inc. has consistently used the percentage-of-completion method of recognizing income. During 2006, Hansen started work on a $3,000,000 fixed-price construction contract. The accounting records disclosed the following data for the year ended December 31, 2006:

align=”left”>

Costs incurred

$ 930,000

Estimated cost to complete

2,170,000

Progress billings

1,100,000

Collections

700,000

How much loss should Hansen have recognized in 2006?

  1. $230,000
  2. $100,000
  3. $ 30,000
  4. $0