The Kalahari Company has received a request for a price quotation from one of its regular customers for an order of 500 units with the following characteristics:

Direct labour per unit produced

2 hours

Direct materials per unit produced

£22

Machine hours per unit produced

1 hour

Number of component and material purchases

6

Number of production runs for the components prior to assembly

4

Average set-up time per production run

3 hours

Number of deliveries

1

Number of customer visits

2

Engineering design and support

50 hours

Customer support

50 hours

Details of the activities required for the order are as follows:

Activity

Activity cost driver rate

Direct labour processing and assembly activities

10 per labour hour

Machine processing

£30 per machine hour

Purchasing and receiving materials and

components

£100 per purchase order

Scheduling production

£250 per production run

Setting-up machines

£120 per set-up hour

Packaging and delivering orders to customers

£400 per delivery

Invoicing and accounts administration

£120 per customer orde

Marketing and order negotiation

r £300 per customer visit

Customer support activities including after

sales service

£50 per customer service hour

Engineering design and support

£80 per engineering hour