Stromski Corporation manufactures a single product. The standard cost per unit of product is shown below.

Direct materials 1 pound plastic at $7.00 per pound $ 7.00

Direct labor 1.5 hours at $12.00 per hour 18.00

Variable manufacturing overhead 11.25

Fixed manufacturing overhead 3.75

Total standard cost per unit $40.00

The predetermined manufacturing overhead rate is $10 per direct labor hour ($15.00 Af· 1.5). It was computed from a master manufacturing overhead budget based on normal production of 7,500 direct labor hours (5,000 units) for the month. The master budget showed total variable costs of $56,250 ($7.50 per hour) and total fixed overhead costs of $18,750 ($2.50 per hour). Actual costs for October in producing 4,900 units were as follows.

Direct materials (5,100 pounds) $ 37,230

Direct labor (7,000 hours) 87,500

Variable overhead 56,170

Fixed overhead 19,680

Total manufacturing costs $200,580

The purchasing department buys the quantities of raw materials that are expected to be used in production each month. Raw materials inventories, therefore, can be ignored.

Compute all of the materials and labor variances. (Round intermediate calculations to 2 decimal places, e.g. 12.50 and final answers to 0 decimal places, e.g. 125.)

Total materials variance $

Materials price variance $

Materials quantity variance $

Total labor variance $

Labor price variance $

Labor quantity variance $

Compute the total overhead variance.