The following data have been recorded for recently completed Job 674 on its job cost sheet. Direct materials cost was $2,127. A total of 32 direct labor hours and 256 machine hours were worked on the job. The direct labor wage rate is $20 per labor hour. The company applies manufacturing overhead on the basis of machine hours. The predetermined overhead rate is $27 per machine hour. The total cost for the job on its job cost sheet would be:

$11,824
$6,635
$7,054
$9,679