Gorman Construction Co. began operations in 2013. Construction activity for 2013 is shown below. Gorman uses the completed contract method.

Billings Collections Contract Costs Estimated
Contract Through Through Incurred Through Additional Costs
Contract Price 12/31/13 12/31/13 12/31/13 to Complete
1 $3,200,000 $3,150,000 $2,600,000 $2,150,000 %u2014
2 3,600,000 1,500,000 1,000,000 820,000 $1,880,000
3 3,300,000 1,900,000 1,800,000 2,250,000 1,200,000

Which of the following should be shown on the income statement for 2013 related to Contract 1?

Gross profit, $1,000,000

Gross profit, $1,050,000

Gross profit, $600,000

Gross profit, $450,000