Problem 5: 10 points

Caballero Manufacturing incurs unit costs of $7.90 ($6.10 variable and $1.80 fixed) in making a sub assembly part for its finished product. A supplier offers to make 12,500 of the assembly part at $5.75 per unit. If the offer is accepted, Caballero will save all variable costs but no fixed costs.

Instructions: Prepare an analysis showing the total cost savings, if any, Caballero will realize by buying the part.

Make

Buy

Total annual cost

Caballero Company should _______________ the part because total annual costs to
make are less than total costs to buy.