Long Term Construction Contracts The Fender Construction Company receives a contract to build a building over a period of three years for a price of $700,000. Information relating to the performance of the contract is summarized as follows:

2007

2008

2009

Construction costs incurred during the year

$150,000

$242,000

$168,000

Estimated costs to complete

350,000

168,000

Billings during the year

120,000

250,000

330,000

Collections during the year

100,000

260,000

340,000

Required

Prepare journal entries for all three years under (1) the percentage of completion method, and (2) the completed contract method.