Percentage of Completion Newberg Construction Corporation contracted to construct a building for $400,000. Construction began in 2007 and was completed in 2008. Data relating to the contract are as follows:

Year Ended December 31,

2007

2008

Costs incurred

$200,000

$110,000

Estimated costs to complete

100,000

Required

Newberg uses the percentage of completion method as the basis for income recognition. For the years ended December 31, 2007 and 2008, respectively, how much income should Newberg report?