Percentage of Completion The Koolman Construction Company began work on a contract in 2007. The contract price is $3,000,000, and the company uses the percentage of completion method. Other information relating to the contract is as follows:

2007

2008

Costs incurred during the year

$600,000

$700,000

Estimated costs to complete, December 31

1,400,000

1,200,000

Billings during the year

500,000

850,000

Collections during the year

400,000

800,000

Required

1. Compute the gross profit or loss recognized in 2007 and 2008.

2. Prepare the appropriate sections of the income statement and ending balance sheet for each year.