(Cost assignment; WA) CushionRide manufactures automobile springs. Its production equipment is fairly old, and one bad unit is typically produced for every 20 good units. The bad units cannot be reworked and must be discarded. Spoilage is determined at an end of process inspection point. CushionRide uses a weighted average process costing system and adds all material at the beginning of the process. The following data have been gathered from the accounting records for January 2001:

Beginning inventory (60% complete as to conversion)

4,000 units

Units started

20,000 units

Ending inventory (30% complete as to conversion)

3,000 units

Good units completed

20,000 units

Material

Conversion

Total

Beginning inventory

$ 12,492

$ 9,927

$ 22,419

Current period

112,548

63,000

175,548

Total costs

$125,040

$72,927

$197,967

a. Prepare an EUP schedule.

b. Determine the cost of the normal spoilage and allocate that cost to the appropriate inventory.