From the following particulars, calculate the earnings of workers A and B under the piece rate system:
|
Standard time allowed: 10 units per hour |
|
Normal time rate per hour: Re 1 |
|
Differential to be applied: |
|
80% of piece rate when below standard |
|
120% of piece rate at or above standard |
|
In a day of 8 hours, |
|
A produced 75 units |
|
B produced 100 units |
|
A (Rs) |
B (Rs) |
|
|---|---|---|
|
Straight piece rate |
7.5 |
10 |
|
Taylor’s differential piece rate |
6 |
12 |