What is HiTech’s pool rate for the material handling activity closest to?

A rate other than those listed above.
$1.04 per part.
$3.20 per part.
$8.29 per labor hour.
$16.57 per part.

What is HiTech’s pool rate for the automated machinery activity closest to?

A rate other than those listed above.
$20.02 per machine hour.
$50.42 per unit.
$58.00 per machine hour.
$20.52 per labor hour.

What is HiTech’s pool rate for the finishing activity closest to?

$9.13 per unit.
$6.63 per machine hour.
A rate other than those listed above.
$6.63 per unit.
$6.63 per labor hour.

What is HiTech’s pool rate for the packaging activity closest to?

$6.63 per labor hour.
$6.49 per machine hour.
$11.91 per unit.
A rate other than those listed above.
$119.07 per order shipped.

Under an activity based costing system, what is the per unit overhead cost of Economy?
(Do not round your intermediate calculations round your final answer to 2 decimal places.)

$214.04.
$217.04.
$153.04.
$130.04.
An amount other than those listed above.