HiTech Products manufactures three types of remote control devices: Economy, Standard, and Deluxe. The company, which uses activity based costing, has identified five activities (and related cost drivers). Each activity, its budgeted cost, and related cost driver is identified below.

Activity Cost Cost Driver
Material handling $320,000 Number of parts
Material insertion 2,950,000 Number of parts
Automated machinery 897,000 Machine hours
Finishing 256,000 Direct labor hours
Packaging 256,000 Orders shipped

Total $4,679,000


The following information pertains to the three product lines for next year:

Economy Standard Deluxe
Units to be produced 10,000 7,000 2,300
Orders to be shipped 1,170 740 240
Number of parts per unit 10 20 30
Machine hours per unit 1 3 6
Labor hours per unit 2 2 2

rev: 10_29_2012

What is HiTech’s pool rate for the material handling activity closest to?

$16.57 per part.
$3.20 per part.
$1.04 per part.
$8.29 per labor hour.
A rate other than those listed above.

What is HiTech’s pool rate for the automated machinery activity closest to?

$58.00 per machine hour.
$20.52 per labor hour.
$20.02 per machine hour.
$50.42 per unit.
A rate other than those listed above.

What is HiTech’s pool rate for the finishing activity closest to?

$6.63 per machine hour.
$6.63 per unit.
A rate other than those listed above.
$6.63 per labor hour.
$9.13 per unit.

What is HiTech’s pool rate for the packaging activity closest to?

$6.49 per machine hour.
A rate other than those listed above.
$6.63 per labor hour.
$11.91 per unit.
$119.07 per order shipped.

Under an activity based costing system, what is the per unit overhead cost of Economy?
(Do not round your intermediate calculations round your final answer to 2 decimal places.)

$130.04.
$153.04.
An amount other than those listed above.
$217.04.
$214.04.