A job cost sheet of Battle Company is given below.
Job Cost Sheet |
|||
Job No.469 |
Quantity: 2,000 |
||
Item: White Lion Cages |
Date Requesteed: 7/2 |
||
For: Tesla Company |
Date Completed: 7/31 |
||
Date |
Direct Materials |
Direct labor |
Manufacturing Overhead |
7/10 |
828 |
||
7/12 |
900 |
||
7/15 |
440 |
528 |
|
7/22 |
380 |
456 |
|
7/27 |
1,600 |
||
7/27 |
1,500 |
||
7/31 |
540 |
648 |
Instructions
(a) Answer the following questions.
(1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job?
(2) What is the predetermined manufacturing overhead rate?
(3) What are the total cost and the unit cost of the completed job?
(b) Prepare the entry to record the completion of the job.