Durkee Corporation keeps careful track of the time required to fill orders. The times required for a particular order appear below:

Wait time

Hours: 10.7

Process time

Hours: 0.9

Inspection time

Hours: 0.4

Move time

Hours: 2.3

Queue time

Hours: 4.5

Required:

A.) Determine the throughput time. Show your work!

B.) Determine the manufacture cycle efficiency (MCE), show your work!

C.) Determine the delivery cycle time. Show your work!