Durkee Corporation keeps careful track of the time required to fill orders. The times required for a particular order appear below:
Wait time |
Hours: 10.7 |
Process time |
Hours: 0.9 |
Inspection time |
Hours: 0.4 |
Move time |
Hours: 2.3 |
Queue time |
Hours: 4.5 |
Required:
A.) Determine the throughput time. Show your work!
B.) Determine the manufacture cycle efficiency (MCE), show your work!
C.) Determine the delivery cycle time. Show your work!