Andry Corporation uses activity based costing to determine product costs for external financial reports. The company has provided the following data concerning its activity based costing system:

Activity Cost Pools (and Activity Measures)

Estimated Overhead Cost

Machine related (machine hours)

$177,000

Batch setup (setups)

$453,600

General factory (direct labor hours)

$227,000

 

Expected Activity

Activity Cost Pools

Total

Product X

Product Y

Machine related

10,000

7,000

3,000

Batch setup

7,000

5,000

2,000

General factory

10,000

6,000

4,000

The activity rate for the batch setup activity cost pool is closest to:

A) $122.50

B) $226.80

C) $90.70

D) $64.80