Excellent Erectors Ltd. took up a contract for construction of a building at a contract price of Rs. 15 lakhs. During the first year, the following amounts were spent as against a sum of Rs. 5,62,500, which represented 90%of the work certified and received by the contractor.

Materials

2,62,500

Wages paid to workers

1,50,000

Overhead expenses

37,500

During the second year, the firm spent the following amounts:

Materials

3,75,000

Labour cost

3,00,000

Overhead expenses

75,000

In the second year, the contract was completed and the sum of Rs. 8,75,00 was received by the contractor. Prepare the contract and contractee’s accounts for both the years and calculate the profit.