The following expenses were incurred on a contract that was still unfinished on 31 December 2009:

Materials

1,50,000

Wages

1,30,000

Other expenses

95,000

Rs. 7,50,000 was received from the contractee being 75%of work certified. Work uncertified was Rs. 37,500. You are required to calculate the profit to be credited to P&L A/c:

  1. If the contract price was Rs. 20,00,000
  2. If the contract price was Rs. 30,00,000
  3. If the contract price was Rs. 50,00,000