From the following particulars, compute the machine hour rate

Rs.

Cost of the machine

30,000

Estimated scrap value after the expiry of its life of 5 years

3,000

Rent and rates of the department

2,000

General lighting of the department p.m.

200

Salary of the supervisor p.m.

1,500

Power consumption is 5 units at the rate of 60 paise per unit. Estimated working hours of the machine per year is 2,000. The machine occupiesth of the total area of the department. The supervisor is expected to devoteof the time to this machine. General lighting charges are to be apportioned on the basis of floor area. Rent and rate charges are for three months.