State Co. recognizes construction revenue and expenses using the percentage-of-completion method. During 2005, a single long-term project was begun, which continued through 2006. Information on the project follows:

align=”left”>

2005

2006

Accounts receivable from construction contract

$100,000

$300,000

Construction expenses

105,000

192,000

Construction in progress

122,000

364,000

Partial billings on contract

100,000

420,000

Profit recognized from the long-term construction contract in 2006 should be

  1. $ 50,000
  2. $108,000
  3. $128,000
  4. $228,000