Standard

Actual

Material Cost Per Yard

$2.00

$2.10

Standard Yards per Unit

4.5 yards

4.75 yards

Units of Production

9,500

5. Calculate the Total Direct Materials cost variance using the above information:

a.

$9,262.50 Unfavorable

b.

$9,262.50 Favorable

c.

$3,780.00 Unfavorable

d.

$3,562.50 Favorable

6. Calculate the Direct Materials Price variance using the above information:

a.

$1,795.50 Favorable

b.

$378.00 Favorable

c.

$4,512.50 Unfavorable

d.

$378.00 Unfavorable

7. Calculate the Direct Materials Quantity variance using the above information:

a.

$4,512.50 Unfavorable

b.

$4,512.50 Favorable

c.

$4,750 Unfavorable

d.

$4,750 Favorable