1 | P a g e

Assessment Task 1 — Assignment

Due date: Thursday of Week 9 (4.00 pm AEST)

ASSESSMENT

Weighting: 30% 1

Assessment details for ALL students

Objectives

This assessment item relates to the course learning outcomes 1 7.

Details of the assignment:

Question 1 30 Marks

Glass Designs Ltd manufactures decorative glass bowls. The firm employs a process

costing system for its manufacturing operations. All direct materials are added at the

beginning of the process, and conversion costs are incurred uniformly throughout the

process. The company’s production quantity schedule for March 2013 is as follows:

Units

Work in process on 1 March (60% complete as to conversion) 2,000

Units started during March 10,000

Total units to account for 12,000

Units from beginning work in process, which were completed and

transferred out during March

2,000

Units started and completed during March 6,000

Work in process on 31 March (20% complete as to conversion) 4,000

Total units accounted for 12,000

Cost information:

Costs of Work in process (1 March):

? Materials…………………….. $ 40,000

? Labour ………………………. $ 12,000

? Overhead …………………….$ 6,000

Costs added during the month (March) were as follows:

? Materials…………………….. $ 200,000

? Labour ………………………. $ 76,000

? Overhead …………………….$ 38,000

2 | P a g e

Required:

(a) Prepare a schedule of equivalent units for each cost element for the month of March

using the weighted average method. (6 marks)

(b) Prepare a schedule of equivalent units for each cost element for the month of March

using the first in first out (FIFO) method. (6 marks)

(c) Calculate the cost (to the nearest cent) per equivalent unit for each cost element for

the month of March using the weighted average method. (3 marks)

(d) Calculate the cost (to the nearest cent) per equivalent unit for each cost element for

the month of March using the first in first out (FIFO) method. (3 marks)

(e) Determine the cost of ending work in process and the cost of finished goods

transferred out during March using the weighted average method. (6 marks)

(f) Determine the cost of ending work in process and the cost of finished goods

transferred out during March using the first in first out (FIFO) method. (6 marks)

Question 2 30 Marks

Beta Company Ltd manufactures two products (product X & product Y) in two production

departments (Department 1 & Department 2). Product X is a simple, high volume product

and product Y is a complex, low volume product. Both products are processed in

departments 1 and 2. Product X uses only one raw material (W), but product B uses two raw

materials (W and Z). Table 1 provides data on the production, sales, selling prices and costs

incurred for the last year ended 30 June 2012.

Table 1: Production, Sales, selling prices and Costs

Product X Product Y Costs

Production and Sales 500,000 units 12,500 units

Selling Price per Unit $78 $133

Direct Materials:

Raw material W 60,000 Kilograms 2,000 Kilograms $744,000

Raw Material Z 1,250 units $120,000

Direct Labour:

Department 1 150,000 hours 5,000 hours $2,325,000

Department 2 75,000 hours 2,500 hours $1,550,000

Production Overhead Cost:

Department 1 $9,610,000

Department 2 $6,277,500

Non production Overhead Cost $1,982,120

Under the traditional costing system Beta Company Ltd allocated production overhead cost

to products using departmental overhead rates based on direct labour hours (for both

departments). Non production overhead cost was absorbed on a sales volume basis.

The Manager (Mr Ahmed) argues that traditional costing ignores the different complexity of

products X and Y as it allocates production and non production overhead cost based on

volume based overhead application rates such as direct labour and sales volume.

Beta Company Ltd attempts to overcome the problem of cost distortions resulting from the

traditional costing system. They consider introducing the ABC costing system that attributes

costs to products based on the activities they demand. Table 2 presents the activities, cost

3 | P a g e

drivers and costs identified by Beta Company Ltd’s management accountants for applying

the ABC costing system.

Table 2: Activities, Cost Drivers and Costs

Activities Activity Cost Driver Activity Cost ($)

Received Materials Number of times materials are received 1,250,000

Materials Handlings Number of times materials are moved 1,500,000

Set up of Machines Set up hours 2,400,000

Running of Machines Number of machine hours 5,137,500

Quality Control Number of units inspected 3,100,000

Machine Maintenance Hours of machine maintenance 2,500,000

Delivery to Customer Number of kilometres 1,189,380

Customer Liaison Number of customer visits 792,740

Activity Cost Driver volumes by product are given in Table 3.

Table 3: Activity Cost Driver Volumes

Activity Cost Driver Product X Product Y Total

Number of times materials are received 13,000 7,000 20,000

Number of times materials are moved 90,000 35,000 125,000

Set up hours 30,000 10,000 40,000

Number of machine hours 487,805 12,195 500,000

Number of units inspected 25,000 15,000 40,000

Hours of machine maintenance 100,000 25,000 125,000

Number of kilometres 110,000 40,000 150,000

Number of customer visits 3,750 1,250 5,000

Required:

(a) Calculate full unit cost for products X and Y under the traditional costing system.

(6 marks)

(b) Calculate full unit cost for products X and Y under the new activity based costing

(ABC) system. (9 marks)

(c) Calculate the difference between the full unit cost for products X and Y calculated

under the traditional costing system and that calculated under the ABC costing

system. (3 marks)

(d) Explain the differences calculated in (c) above for both products. (3 marks)

(e) Calculate the difference between product costs of both products and their respective

current selling prices based on the traditional costing system. (3 marks)

(f) Calculate the difference between product costs of both products and their respective

current selling prices based on the ABC costing system. (3 marks)

(g) Identify and explain to Mr Ahmed the possible advantages and disadvantages of

adopting the ABC costing system. (3 marks)

4 | P a g e

Important points

? Use the question numbers to indicate which question you are answering.

? The assignment should be prepared using a Word Processing Package or an excel

sheet.

Submission requirements

You must submit this assignment electronically.

Submit electronic copies of the following two documents:

? your answers to the assignment questions

? a signed assessment cover sheet that is available on the university website

Instructions for generating your cover sheet are at:

http://dtls.cqu.edu.au/FCWViewer/getFile.do?id=23407

Ensure your name and your student ID number appear on your answers and on the

marking criteria sheet.

Assessment criteria

The marking criteria sheet at the end of the assignment indicates the allocation of marks for

the assignment. Please submit an electronic copy of this marking criteria sheet

including your name and your student ID with submitting your assignment.

Note: there is a 5% penalty per day for late submissions.

5 | P a g e

Marking criteria sheet

Student name: Student ID number:

Assessment criteria Your

marks

Total

marks Comments

Question 1

Prepare a schedule of equivalent units for each cost element

for the month of March using the weighted average method 6

Prepare a schedule of equivalent units for each cost element

for the month of March using the FIFO method 6

Calculate the cost (to the nearest cent) per equivalent unit

for each cost element for the month of March using the

weighted average method

3

Calculate the cost (to the nearest cent) per equivalent unit

for each cost element for the month of March using the FIFO

method

3

Determine the cost of ending work in process and the cost of

finished goods transferred out during March using the

weighted average method

6

Determine the cost of ending work in process and the cost of

finished goods transferred out during March using the FIFO

method

6

Total marks for Question 1 30

Question 2

Calculate full unit cost for products X and Y under the

traditional costing system 6

Calculate full unit cost for products X and Y under the ABC

costing system 9

Calculate the difference between the full unit cost for

products X and Y calculated under the traditional costing

system and that calculated under the ABC costing system.

3

Explain the differences calculated in (c) above for both

products. 3

Calculate the difference between product costs of both

products and their respective current selling prices based on

the traditional costing system.

3

Calculate the difference between product costs of both

products and their respective current selling prices based on

the ABC costing system.

3

Identify and explain to Mr Ahmed the possible advantages

and disadvantages of adopting the ABC costing system.

3

Total marks for Question 2 30

Total marks for assignment 60

To be reduced to

a mark out of 30%

Attachments: