During March 2010, Hinton Tool & Die Company worked on four jobs. A review of direct labor costs reveals the following summary data.

Job

Actual

Standard

Total

Number

Hours

Costs

Hours

Costs

Variance

A257

220

$ 4,400

225

$4,500

$ 100 F

A258

450

9,900

430

8,600

1,300 U

A259

300

6,150

300

6,000

150 U

A260

115

2,070

110

2,200

130 F

Total variance

$1,220 U

Analysis reveals that Job A257 was a repeat job. Job A258 was a rush order that required overtime work at premium rates of pay. Job A259 required a more experienced replacement worker on one shift. Work on Job A260 was done for one day by a new trainee when a regular worker was absent.

Instructions

Prepare a report for the plant supervisor on direct labor cost variances for March. The report should have columns for (1) Job No., (2) Actual Hours, (3) Standard Hours, (4) Quantity Variance, (5) Actual Rate, (6) Standard Rate, (7) Price Variance, and (8) Explanation.