The following balances were extracted from the books of a building contractor on 31st March 1976.

Rs

Materials issued to site

62,720

Wages paid

73,455

Wages outstanding as on 31 3 1976

720

Plant issued to site

6,000

Direct charges paid

2,515

Direct charges outstanding on 31 3 1976

210

Establishment charges

5,650

Stock of materials at site on 31 3 1976

1,200

Value of work certified on 31 3 1976

1,65,000

Cost of work not yet certified

3,500

Cash received on account of architect’s certificate

1,41,075

The work was commenced on 1st April 1975 and the contract price agreed at Rs 2,45,000. Prepare contract account for the year, providing for depreciation of plant at 25%. Calculate the profit or loss on the contract to date and make such provision in the contract account, as you consider desirable. Set out also the contractor’s balance sheet so far as it relates to the contract.