A job cost sheet of Sandoval Company is given below.

Job Cost Sheet

JOB NO.

469

Quantity

2,500

ITEM

White Lion Cages

Date Requested

7/2

FOR

Todd Company

Date Completed

7/31

Date

Direct
Materials

Direct
Labor

Manufacturing
Overhead

7/10

700

12

900

15

440

550

22

380

475

24

1,600

27

1,500

31

540

675

Cost of completed job:

Direct materials

Direct labor

Manufacturing overhead

Total cost

Unit cost

Instructions

(a) Answer the following questions.

(1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job?

(2) What is the predetermined manufacturing overhead rate?

(3) What are the total cost and the unit cost of the completed job? (Round unit cost to nearest cent.)

(b) Prepare the entry to record the completion of the job.